Compliance Dates

Existing Sources January 2, 2007
New or Reconstructed Sources Upon startup
Existing Area Sources that Change into Major Source One year after becoming a major source, or January 2, 2007, whichever is later
New or Reconstructed Area Sources that Change into Major Source One year after becoming a major source, or January 2, 2004, whichever is later

Compliance Time-line: Existing Sources - All Compliance Options

Initial Notification January 2, 2005
Begin Collecting Data for Initial Compliance
Demonstration for Initial Compliance Period
January 3, 2007
End Initial Compliance Demonstration January 31, 2008
Notify Local Air Pollution Control Agency of Compliance Status March 1, 2008
Submit Semi-annual Compliance Reports July 31, 2008 and semiannually after that

What is a New or Reconstructed Source?

It started construction after August 13, 2002.
It is a major source upon startup.


It is a completely new miscellaneous metal parts and products surface coating facility where none existed immediately prior to the construction of the facility.

Compliance Time-line: New or Reconstructed Sources - All Compliance Options

Initial Notification May 1, 2004 or 120 days from start-up whichever is later
Begin Collecting Data for Initial Compliance Demonstration for Initial Compliance Period Day after Compliance Date
End Initial Compliance Demonstration Last day of 12th full month after Compliance Date
Notify Local Air Pollution Control Agency of Compliance Status March 2, 2005 or no later than 30 days after the the initial compliance period, whichever is later
Submit Semi-annual Compliance Reports No later than July 31 or January 31, whichever date is the first date after the initial compliance period and semiannually after that

Compliance Time-line: Existing Sources - Option 3

Compliance based on using a capture system and add-on control device

Submit Notification of Intent to Conduct a Performance Test November 3, 2006
Conduct Performance Test January 2, 2007
Develop and Implement Work Practice Plan January 2, 2007
Results of Initial Performance Tests March 3, 2007

Compliance Time-line: New or Reconstructed Sources - Option 3

Compliance based on using a capture system and add-on control device

Submit Notification of Intent to Conduct a Performance Test May 1, 2004 or within 60 days before the performance test is scheduled to begin, whichever is later
Conduct Performance Test June 30, 2004 or no later than 180 days after the compliance date, whichever is later
Develop and Implement Work Practice Plan January 2, 2004 or initial startup, whichever is later
Results of Initial Performance Tests August 29, 2004 or within 60 days after completing the performance test, whichever is later