The University of Tennessee Institute for Public Service
A-Z Index / WebMail / Dept. Directory
Center for Industrial Services

MACT Rules

More Info




arrow

Plastic Parts Coating MACT: compliance Timeline

Surface Coating of Plastic Parts and Products (69 FR 20968)

 

Note:  These timelines do not take into account special situation such as compliance extensions.

 

A. Existing Sources

 

Event

Timeline

Effective Date

April 19, 2004

Submit Initial Notification

No later than April 19, 2005 [63.4510(b)]

Compliance Date

 

 

April 19, 2007 [63.4493(b)]

 

Area Source that becomes a major source:  April 19, 2007 or one year after the area source becomes an existing major source, whichever is later. [63.4483(c)(2)]

Conduct Initial Compliance Demonstrations

 

The initial compliance demonstration must be completed for the initial compliance period, which begins on April 30, 2007, and ends on April 30, 2008 [63.4540, 63.4550, 63.4560(b)(3)].

Submit Notification of Intent to Conduct a Performance Test

 

Note: Applies to add-on controls option only.

No later than February 18 2007 [63.7(b) and63.9(e)]

Conduct Performance Test

 

Note:  Performance tests must be performed for each capture system and add-on control device, except for solvent recovery systems.  For solvent recovery systems, the first material balance must be initiated.

 

No later than April 19, 2007 [63.4560(b)(1)]

Develop and Implement Work Practice Plan

 

Note: Work practice plans must be developed for compliance with the add-on controls option only.

 

No later than April 19, 2007 [63.4560(b)(2)]

Results of Initial Performance Tests

 

 

No later than June 18, 2007 [63.4520(b)]

Notification of Compliance Status

 

 

No later than May 30, 2008 [63.4510(c)]

Semiannual Compliance Reports

 

 

July 31, 2008 and every January 31 and July 31 thereafter [63.4520(a)(1)]

 

 

B. All New or Reconstructed Sources

 

Note: New affected source: an affected source that the construction or reconstruction of which commenced after December 4, 2002 [63.4482(c)].

 

Event

Timeline

Effective Date

April 19, 2004  [69 FR 20968]

Submit Initial Notification

August 17, 2004 or within 120 days from start-up, whichever is later  [63.4510(b)]

Compliance Date

 

 

Upon startup or April 19, 2004, whichever is later  [63.4483(a)]

 

Area Source that becomes a major source:  April 19, 2004 or upon becomes a new major source, whichever is later. [63.4483(c)(1)]

Conduct Initial Compliance Demonstrations

 

The initial compliance demonstration must be completed for the initial compliance period, which begins on the day after the compliance date and ends on the last day of the 12th full month after the compliance date [63.4540, 63.4550 or 63.4560(a)(3)]

Submit Notification of Intent to Conduct a Performance Test

 

Note: Applies to add-on controls option only.

By August 17, 2004 or within 60 days before the performance test is scheduled to begin, whichever is later [63.7(b) and 63.9(e)]

Conduct Performance Test

 

Note:  Performance tests must be performed for each capture system and add-on control device, except for solvent recovery systems.  For solvent recovery systems, the first material balance must be initiated.

October 16, 2004 or no later than 180 days after the compliance date, whichever is later [63.4560(a)(1)]

Develop and Implement Work Practice Plan

 

Note: Work practice plans must be developed for compliance with the add-on controls option only.

April 19, 2004, or initial startup, whichever is later [63.4560(a)(2)]

Results of Initial Performance Tests

 

 

December 15, 2004 or within 60 days after completing the performance test, whichever is later [63.4520(b)]

Notification of Compliance Status

May 30, 2005 or no later than 30 days following the end of the initial compliance period, whichever is later [63.4510(c)]

 

Note:  The initial compliance period begins on the day after the compliance date and ends on the last day of the 12th full month after the compliance date [63.4540, 63.4560(a)(3) and (b)(3)].

Semiannual Compliance Reports

 

 

 

Every January 31 and July 31, after the end of the initial compliance period.

 

Note: The initial semiannual report must cover the period beginning on the day after the end of the initial compliance period and ends on June 30 or December 31, whichever  date is the first date following the end of the initial compliance period. [63.4520(a)(1)

 



Trouble with PDF files? Download the latest version of Acrobat Reader.