| Proposed Rule: |
4/04/02 |
| Final Rule: |
11/10/03 |
| Existing Sources: |
11/10/06 |
| New Sources: |
Upon Startup |
| New Sources before 11/10/03: |
No later than 11/10/03 |
| MON Rule Effective Date |
11/10/03 |
| Initial Notifications |
03/09/04 |
| Precompliance
Report |
05/06/06 |
| Compliance Extension Request, if
allowed |
12 to18 months prior to Compliance
Date |
| Compliance Date |
11/10/06 |
| Performance Test Notification |
At least 60 days before scheduled
test |
| Notification of Compliance Status
Report (NOCSR) |
4/07/07 |
| Compliance Report |
08/31/07 and every 6 months thereafter |
| MON Rule Effective Date after 11/10/03 |
Upon startup |
| Initial Notifications |
120 days after initial startup |
| Precompliance Report |
With application for approval or construction or reconstruction |
| Compliance Date |
Initial startup |
| Performance Test Notification |
At least 60 days before scheduled test |
| Notification of Compliance Status Report (NOCSR) |
No more than 150 days after the compliance date, i.e. initial
startup |
| Compliance Report |
First August 31 or February 28 following the end of the compliance
period that occurs more than 6 months after the compliance
date. Then every 6 months. |