Miscellaneous Coating Manufacturing: TIMELINE
Compliance Timeline (See Note 1)
Miscellaneous Coating Manufacturing NESHAP
40 CFR Part 63 Subpart HHHHH
Event |
Timeline |
Effective Date |
December 11, 2003 |
Initial Notification submittal |
April 9, 2004 |
Submit notification of planned performance test
|
At least 60 days before the test.
Test to demonstrate initial compliance must be conducted before May 10, 2007 |
Pre-compliance report submittal |
No later than June 11, 2006 |
Compliance Date |
December 11, 2006 (See Note 2) |
Notification of compliance status report submittal |
No later than May 10, 2007 |
First semiannual reporting period |
Ends June 11, 2007 |
First compliance report submittal |
No later than August 8, 2007
Subsequent reports are due 6 months after the preceding report |
Notes:
- Dates shown are for existing sources. For new sources, the intervals between events are the same, but the compliance date is the date of startup. Additionally, the initial notifications does not apply, but a request for approval of construction or reconstruction must be submitted.
- If coating manufacturing operations are included in a process unit group (PUG) under subpart FFFF, the compliance date is May 10, 2008.
|